Environmental / Civil Construction Services

NEWS

Sauro's Cleanerama

Clearcreek Contractors is currently near completion on a US EPA Brownfields project in Tacoma (the former Sauro’s Cleanerama). Brownfields are areas that were used for industrial purposes and because of contamination are currently abandoned, unused, or under-used. This EPA program assists in cleaning up these sites to not only protect the environment but to also reduce blight and help in area redevelopment. Information can be found at - http://epa.gov/brownfields/ and http://www.nebc.org/Documents/brownfields09/4C-Wynkoop.pdf. Sauro’s Cleanerama operated in downtown Tacoma as a dry cleaner from 1961 until 2000. Subsequent to Sauro’s Cleanerama departure, structures on the site were demolished and the property remained vacant. In January 2009, the City of Tacoma purchased the property and two contiguous properties with the intent to remediate and redevelop. A Remedial Investigation/Feasibility Study and Interim Remedial Action Plan (IRAP) were developed and approved in July 2009. Clearcreek Contractors submitted a bid to conduct remedial action for this project and was awarded the contract in August 2009. Clearcreek initiated site activities in September 2009.
Site Conditions/Challenges
• Site encompasses approximately 15,000 square-feet bordered by a multi-story commercial building and three public rights-of-way
• Single access point for ingress/egress
• Pre-construction site elevations one to two stories below surrounding elevations
• Fill material and construction debris present from surface grade to approximately 32 below ground surface
• Existing retaining and gravity walls, columns and footings present within perimeter of site
• Deteriorating vaulted sidewalks along northern and western perimeters of the site
• 10-foot “buffer-zone” from retaining walls back to public rights-of-way where equipment and materials were prohibited
• Drill through fill and debris to accommodate installation of soldier pile and tie-back anchors
• Three separate categories of material designated for disposal

Overall, the IRAP included the installation of soldier pile, tie-backs and lagging wall on three sides of the site to accommodate excavation of impacted soil and debris down to groundwater while maintaining stability of adjacent roadways and retaining walls. “Slot-cut sloping” was conducted to remove impacted soil along the multi-story commercial building footings. Upon reaching the engineered shoring design depth, structural fill was imported and placed up to an elevation above the seasonal high groundwater elevation.

One of the critical componets of the project to accommodate remedial excavation activities and protect adjacent roadways and retaining walls was the installaation of 58 soldier piles along the inside of the existing retaining walls. Upon successful completion of soldier pile installation horizontal drilling was completed and excavation commenced. To date Clearcreek has excavated, transported and disposed of over 12,000 tons of contaminated soil.

Did You Know?

Many of our clients are interested in Permeable Reactive Barrier walls, Soil Cement Barrier walls, and slurry walls yet assume these remediation/containment methods are only viable for large projects due to cost. However, treatment or containment walls less than 100 ft. in length may be cost effective. Clearcreek has experience in installing these remediation systems for large and smaller sized projects. We have the skill sets, personnel, tools, and equipment on-hand to allow us to be cost effective for smaller sized projects. Give us the chance to discuss with you the installation of one of these systems. We will work to ensure your project needs are met. As always, we are committed in assisting you in accomplishing your goals.

 

home | about us | projects | services | news | corporate information | safety | contact list